Box 23
Container
Contains 13 Results:
Table of Contents
File — Box: 23, Folder: 1
Identifier: VII
Scope and Contents
Box 23 contains tabulation of staking sheets and planning units for replacement of old line.
Pole and wire units.
Pole and wire units.
Dates:
1905-1971
Pole Top Units
File — Box: 23, Folder: 2
Identifier: VII
Scope and Contents
From the Sub-Series:
This project involved the reconstruction and upgrading of a distribution line system in Nevada. The line ran from a substation about 15 miles south of Alamo, Nevada to a point one mile north of Hyko, Nevada, serving the community of Alamo and a number of farms and ranches in the Pahranagat Valley. Adams was project engineer through completion.
Dates:
1905-1971
Conversion
File — Box: 23, Folder: 3-5
Identifier: VII
Scope and Contents
From the Sub-Series:
This project involved the reconstruction and upgrading of a distribution line system in Nevada. The line ran from a substation about 15 miles south of Alamo, Nevada to a point one mile north of Hyko, Nevada, serving the community of Alamo and a number of farms and ranches in the Pahranagat Valley. Adams was project engineer through completion.
Dates:
1905-1971
Guys, Anchors, Grounds
File — Box: 23, Folder: 6
Identifier: VII
Scope and Contents
From the Sub-Series:
This project involved the reconstruction and upgrading of a distribution line system in Nevada. The line ran from a substation about 15 miles south of Alamo, Nevada to a point one mile north of Hyko, Nevada, serving the community of Alamo and a number of farms and ranches in the Pahranagat Valley. Adams was project engineer through completion.
Dates:
1905-1971
Removal of Guys, Anchors, Grounds
File — Box: 23, Folder: 7
Identifier: VII
Scope and Contents
From the Sub-Series:
This project involved the reconstruction and upgrading of a distribution line system in Nevada. The line ran from a substation about 15 miles south of Alamo, Nevada to a point one mile north of Hyko, Nevada, serving the community of Alamo and a number of farms and ranches in the Pahranagat Valley. Adams was project engineer through completion.
Dates:
1905-1971
Construction Bulletin; Purchase Orders; Billings for Engineer Service; Pumps and Irrigation
File — Box: 23, Folder: 8
Identifier: VII
Scope and Contents
From the Sub-Series:
This project involved the reconstruction and upgrading of a distribution line system in Nevada. The line ran from a substation about 15 miles south of Alamo, Nevada to a point one mile north of Hyko, Nevada, serving the community of Alamo and a number of farms and ranches in the Pahranagat Valley. Adams was project engineer through completion.
Dates:
1905-1971
Reference Data and Reports; Computations
File — Box: 23, Folder: 9
Identifier: VII
Scope and Contents
From the Sub-Series:
This project involved the reconstruction and upgrading of a distribution line system in Nevada. The line ran from a substation about 15 miles south of Alamo, Nevada to a point one mile north of Hyko, Nevada, serving the community of Alamo and a number of farms and ranches in the Pahranagat Valley. Adams was project engineer through completion.
Dates:
1905-1971
Maps and Diagrams
File — Box: 23, Folder: 10-11
Identifier: VII
Scope and Contents
From the Sub-Series:
This project involved the reconstruction and upgrading of a distribution line system in Nevada. The line ran from a substation about 15 miles south of Alamo, Nevada to a point one mile north of Hyko, Nevada, serving the community of Alamo and a number of farms and ranches in the Pahranagat Valley. Adams was project engineer through completion.
Dates:
1905-1971
Miscellaneous Data
File — Box: 23, Folder: 12
Identifier: VII
Scope and Contents
From the Sub-Series:
This project involved the reconstruction and upgrading of a distribution line system in Nevada. The line ran from a substation about 15 miles south of Alamo, Nevada to a point one mile north of Hyko, Nevada, serving the community of Alamo and a number of farms and ranches in the Pahranagat Valley. Adams was project engineer through completion.
Dates:
1905-1971
Materials Proposals for Line Construction from Various Bidders
File — Box: 23, Folder: 13-24
Identifier: VII
Scope and Contents
From the Sub-Series:
This project involved the reconstruction and upgrading of a distribution line system in Nevada. The line ran from a substation about 15 miles south of Alamo, Nevada to a point one mile north of Hyko, Nevada, serving the community of Alamo and a number of farms and ranches in the Pahranagat Valley. Adams was project engineer through completion.
Dates:
1905-1971