Materials Proposals for Line Construction from Various Bidders

 File — Box: 23, Folder: 13-24
Identifier: VII

Scope and Contents

From the Sub-Series: This project involved the reconstruction and upgrading of a distribution line system in Nevada. The line ran from a substation about 15 miles south of Alamo, Nevada to a point one mile north of Hyko, Nevada, serving the community of Alamo and a number of farms and ranches in the Pahranagat Valley. Adams was project engineer through completion.

Dates

  • 1905-1971

Conditions Governing Access

Twenty-four hour advanced notice encouraged. Materials must be used on-site. Access to parts of this collection may be restricted under provisions of state or federal law.

Extent

From the Collection: 35 Linear Feet